Monday, February 21, 2011

My Life in Sandakan

It is  heavy rain this morning,. The rain only stop at about 11am. I went out with RE Lau to have a drink at the Tien Kee restraurant. We discussed about how rain will affect our work progress; most of the external work will be unable to proceed, also since roofing sheet is not is placed, internal work like plastering, screeding, and brickwork will not be able to carry out at all!
What we hope the letter of eot is yet to be issued by architect, therefore the renewal of insurance is still pending. As contract will be end at the end of this month, pressure is mounting on everyone involve in this project how to find ways to expedite the remaining works.

No comments:

Post a Comment